The EnerPHit Standard

Figure 1: EnerPHit Seal

Achieving the Passive House Standard in refurbishments of existing buildings is not always a realistic goal, one of the reasons being that basement walls remain as barely avoidable thermal bridges even after refurbishment. In order to facilitate the achievement of an optimal standard of thermal protection in building refurbishments, the EnerPHit certification procedure was launched by the Passive House Institute in 2010. An optimal standard of thermal protection means a significantly better level of energy efficiency compared to the legal requirements must simultaneously go hand-in-hand with high cost efficiency of the thermal protection measures as a whole. At the same time, modernisation to the EnerPHit Standard also offers other advantages associated with the use of Passive House components, such as an excellent level of thermal comfort, structural integrity and high quality indoor air. The primary aim of this certification is to provide quality assurance for the refurbishment so that the building owner can be sure that the stipulated optimal standard of thermal protection is actually achieved and that the implemented measures prove to be adequate. This is all the more important because subsequent "correction" of inadequate thermal protection measures almost always proves to be uneconomical. The EnerPHit standard requires either a maximum heating demand of 25 kWh/(m²a) (in central Europe) or alternatively the consistent use of Passive House components in accordance with the requirements for PHI certification of components. The heating demand calculated by the PHPP, and the quality of thermal protection of the individual components are indicated in the certificate.

Step-by-step retrofits

At present, EnerPHit certification can be achieved if all energy related building components have been modernised completely using Passive House components. However, often times many buildings are modernised in a step-by-step manner with long time intervals in between each step. Statistics of the German national efficiency funding programmes of the KfW-Bank show that approximately 2/3 of all funded projects consisted of single or multiple retrofit measures. It thereby is assumed that a majority of retrofits is carried out partially, often single measures only, and buildings are not improved to a high efficiency level such as EnerPHit in the first shot. There are a lot of reasons which may lead to stepwise refurbishment of a building. For step-by-step retrofitting, the retrofit concept to be chosen leads to various approaches and depends on several factors, such as budget availability, disturbance of inhabitants, life cycle of components or competence of the designer and motivation of the investor. In general, stepwise retrofits can be sorted into two main categories such as

1. Stepwise retrofitting of a building component by component

In this case, the whole building is being modernised, but only one or several components. For example, in a first step, insulation of the building envelope is applied, in a second step the windows and airtightness are installed, and in a last step, a ventilation system and heating and RES concepts are implemented, as can be seen in Figure 2 below:

Figure 2: Stepwise retrofits component by component
Figure 3: Partial retrofits part by part


2. Partial retrofitting of a building part by part

Buildings may also be retrofitted not as a whole, but partially. Starting with a section of the building only, then including all or at least most components, the efficiency of a certain part of the building is updated. This part can either consist of a building side or façade, a single or several flats or even whole building sections, as illustrated above in the Figure 3.

Shallow retrofits lead to lock in effects

Figure 4: High reduction potentials for step-by-step retrofits

Either way, systematic planning or quality assurance is rarely carried out in such instances. In many countries, single measures do not even require a building authority approval. Thereby, in many cases a qualified designer or consultant won´t even be involved. The quality measures will be designed and chosen based on budget and competence of the investor or building owner and carried out by a contractor with a more or less moderate knowledge on building efficiency. This may, however, lead to shallow retrofit measures, and also measures which might compromise high efficiency standards of later retrofit steps, thereby create lock in effects. In order to achieve highest efficiency for retrofits of the building stock, thereby CO2 emission reductions of 80% or higher, single retrofit measure of step-by-step retrofits should be carried out according to high quality standards and a sound retrofit concept.
















Overall refurbishment plans for stepwise retrofit approaches

Figure 5: PHPP 9 with data entry of retrofit steps
So, instead of retrofitting a single component now and identify problems with following measures later, setting up an overall retrofit plan is the proper way to do it. Even though the initial effort for setting up such a plan, the creation of such a document makes sense, enabling the investor or building owner to have an overview over the efficiency properties of his building, the retrofit requirements and schedule and the reduction potentials for energy consumption and CO2 emissions.

  • First the existing building needs to be analysed, energy consumption, known problems and component life cycles taken into account
  • As a next step, the existing building needs to be entered into the PHPP 9. Then suggested measures can be entered separately as retrofit steps in PHPP 9, as variants to the existing building. The final step will illustrate that the efficiency improvements to be carried out will enable the building to fulfil EnerPHit standard.
  • Descriptions of the retrofit steps and measures needs to be set up and a schematic diagram of the chronological flow of the modernisation steps or set of measures will be created.
  • Additionally, it is recommended to follow a checklist for typical considerations with the sequential order (e.g. airtightness before installation of the ventilation system; renewal of the heating system before optimisation of the thermal protection, insulation of the floor before replacement of French windows etc.).
  • Specific connection details between components and spate retrofit steps will need to be roughly be sketched. In these sketches the airtightness-layer needs to be indicated and described.


An overall refurbishment plan set up like this allows the building owner to understand the retrofit concept, required component qualities and dependencies of the separate retrofit steps. Just as well, the contractors, who will carry out the retrofit steps have this document as guideline for their work.



New certification concept for step-by-step retrofits

Figure 6: Step-by-step certification scheme for EnerPHit retrofits

As a result, the Passive House Institute is currently developing a quality assurance system for step-by-step refurbishments. The focus of this new certification process is an overall concept for modernisation which includes all energy-relevant building components and defines reasonable thermal protection standards and completion times for each of these. In addition, the position of the insulation layer and the airtight level are defined for the future steps in advance so that connections of building components can be implemented in an airtight and thermal bridge free manner at a later time. Dependencies between different building components are considered, using a checklist, so that a coherent and viable overall concept can be developed.

All modernisation steps will then be entered into a new version of the Passive House Planning Package (PHPP) which has been optimised for this purpose. After the overall concept has been reviewed by a PHI-accredited certifier and the first modernisation step has been implemented, the concept can be certified. This confirms that the EnerPHit Standard will be achieved following the successful implementation of all modernisation steps as planned. This review is a precursor to the EnerPHit certification which may only take place years later after the overall refurbishment is completed.
Following this concept, it is guaranteed that a retrofit plan started can be carried out according to the highly ambitious concept that was foreseen from the start, even over a bigger time span of many years.

Thereby, even in case of the change of the building owner, the consultant or contractors, the basic concept and requirements for the deep retrofit approach are always comprehensive and available. To allow a continuous work-flow for long time retrofit processes, the certification scheme also offers to store the relevant document such as plan materials, details, component datasheets or PHPP calculation on a Certification Platform, that supports a streamlined certification process and documentation over many years.




Exemplary implementation of pilot projects

Figure 7: Case study projects illustrating step-by-step approaches
The certification process described above as well as the certification platform have been developed in the European IEE funding project EuroPHit. In this project, practical pilot projects of step-by-step retrofits are carried out to gain practical experiences with the certification process, set up catalogues with exemplary construction details, videos of installation procedures, and guides for modernisation pro-cesses will be developed and made available. In addition, the planning and expert teams involved in these pilot projects will be trained for the specific requirements of step-by-step refurbishment projects.











Further information regarding EuroPHit can be found online at: www.europhit.de